[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119858":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119858,789,1,"单选题","对于承包人向发包人的索赔请求，索赔文件首先应该交由()审核。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主",false,{"key":16,"text":17,"correct":18},"B","工程师",true,{"key":20,"text":21,"correct":14},"C","项目经理",{"key":23,"text":24,"correct":14},"D","律师","2021\u002F2020教材P264页 “对于承包人向发包人的索赔请求，索赔文件应交由工程师（监理人）审核”，",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]