[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119854,789,1,"单选题","承包人必须在发出索赔意向通知后的( )天内或经过工程师（监理人）同意的其他合理时间内向工程师（监理人）提交一份详细的索赔文件和有关资料。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","56","2021\u002F2020教材P263页 承包人必须在发出索赔意向通知后的28天内或经过工程师（监理人）同意的其他合理时间内向工程师（监理人）提交一份详细的索赔文件和有关资料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]