[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119853,789,1,"单选题","索赔资料准备阶段的主要工作，不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","跟踪和调查干扰事件，掌握事件产生的详细经过",false,{"key":16,"text":17,"correct":14},"B","分析干扰事件产生的原因，划清各方责任，确定索赔根据",{"key":19,"text":20,"correct":14},"C","损失或损害调查分析与计算，确定工期索赔和费用索赔值",{"key":22,"text":23,"correct":24},"D","提交索赔意向通知和索赔报告",true,"2021\u002F2020教材P263页 在索赔资料准备阶段，主要工作有：(1)跟踪和调査干扰事件，掌握事件产生的详细经过；(2)分析干扰事件产生的原因，划清各方责任，确定索赔根据；(3)损失或损害调查分析与计算，确定工期索赔和费用索赔值；(4)收集证据，获得充分而有效的各种证据；(5)起草索赔文件(索赔报告）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]