[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119847,789,1,"单选题","施工合同索赔程序的第一步是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人收集证据",false,{"key":16,"text":17,"correct":14},"B","承包人提交索赔报告",{"key":19,"text":20,"correct":14},"C","监理人审核索赔报告",{"key":22,"text":23,"correct":24},"D","承包人向监理人提交索赔意向通知书",true,"2021\u002F2020教材P263页 一、索赔意向通知和索赔通知在工程实施过程中发生索赔事件以后，或者承包人发现索赔机会，首先要提出索赔意向，即在合同规定时间内将索赔意向用书面形式及时通知发包人或者工程师（监理人），向对方表明索赔愿望、要求或者声明保留索赔权利，这是索赔工作程序的第一步。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]