[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119845":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119845,789,1,"单选题","下列材料属于索赔意向通知内容的是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","索赔金额",false,{"key":16,"text":17,"correct":14},"B","承包人为该索赔事项付出的附加开支",{"key":19,"text":20,"correct":14},"C","索赔工期的计算",{"key":22,"text":23,"correct":24},"D","索赔依据",true,"2021\u002F2020教材P263页 索赔意向通知要简明扼要地说明以下四个方面的内容： (1)索赔事件发生的时间、地点和简单事实情况描述； (2)索赔事件的发展动态； (3)索赔依据和理由； (4)索赔事件对工程成本和工期产生的不利影响。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]