[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119843,789,1,"单选题","某承包商承揽的写字楼工程，由于场地中间有几户居民不搬迁，工程不能按期开工。承包商向业主（监理工程师）发出索赔意向书后，依然迟迟不能开工情况下，承包商应该按照工程师要求的合理间隔期，提交（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","新的索赔意向书",false,{"key":16,"text":17,"correct":18},"B","延续索赔通知",true,{"key":20,"text":21,"correct":14},"C","新的索赔证据和依据",{"key":23,"text":24,"correct":14},"D","最终索赔报告","2021\u002F2020教材P263页 “索赔事件具有连续影响的，承包人应按合理事件间隔继续递交延续索赔通知”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]