[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119842,789,1,"单选题","根据《标准施工招标文件》，发生发包人索赔事件后，监理人应及时书面通知承包人，详细说明索赔金额和（或）延长缺陷责任期的细节和依据，发包人提出索赔的期限和要求应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","视工程具体情况而不同",false,{"key":16,"text":17,"correct":14},"B","在《标准施工招标文件》中没有规定",{"key":19,"text":20,"correct":21},"C","与承包人提出索赔的期限和要求相同",true,{"key":23,"text":24,"correct":14},"D","与承包人协商以后确定","2021\u002F2020教材P263页 “根据九部委《标准施工招标文件》中的通用合同条款，发生发包人的索赔事件后，监理人应及时书面通知承包人，详细说明发包人有权得到的索赔金额和（或）延长缺陷责任期的细节和依据。发包人提出索赔的期限和要求与承包人提出索赔的期限和要求相同，延长缺陷责任期的通知应在缺陷责任期届满前发出”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]