[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119841":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119841,789,1,"单选题","承包商在施工过程中，由于设计变更的个别施工图纸变更拖延，造成工程局部施工拖延约3个月，在这种情况下，承包商向发包人提出工期和费用索赔，其工作程序应该是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","索赔意向通知书--------索赔通知书--------延续索赔通知书--------最终索赔通知书",true,{"key":16,"text":17,"correct":18},"B","索赔意向通知书--------延续索赔通知书--------最终索赔通知书",false,{"key":20,"text":21,"correct":18},"C","索赔意向通知书--------延续索赔通知书",{"key":23,"text":24,"correct":18},"D","索赔意向通知书--------索赔通知书","2021\u002F2020教材P263页 “根据合同约定，承包人认为有权得到追加付款和延长工期的，应按以下程序向发包人提出索赔：（1）承包人应在知道或应当知道索赔事件放生后28内，向监理人递交索赔意向通知书；（2）承包人应在发出索赔意向通知书后28天内，向监理人正式递交索赔通知书；（3）索赔事件具有连续影响的，承包人应按合理事件间隔连续递交延续索赔通知；（4）在索赔事件影响结束后的28天内，承包人应向监理人递交最终索赔通知书”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]