[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119840":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119840,789,1,"单选题","根据《标准施工招标文件》，在索赔事件影响结束后的28天内，承包人应向监理人递交()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","索赔意向通知",false,{"key":16,"text":17,"correct":14},"B","中间索赔报告",{"key":19,"text":20,"correct":21},"C","最终索赔报告",true,{"key":23,"text":24,"correct":14},"D","索赔证据","2021\u002F2020教材P263页 (4)在索赔事件影响结束后的28天内，承包人应向监理人递交最终索赔通知书，说明最终要求索赔的追加付款金额和延长的工期，并附必要的记录和证明材料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]