[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119839":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119839,789,1,"单选题","根据九部委《标准施工招标文件》，承包人提交了索赔文件后，干扰事件对施工造成持续影响，这种情况下承包人的正确做法位（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","只需在干扰事件影响结束后28d内提交最终索赔报告",false,{"key":16,"text":17,"correct":18},"B","按工程师要求的间隔提交延续索赔通知，干扰事件影响结束后28d内提交最终索赔报告",true,{"key":20,"text":21,"correct":14},"C","按工程师要求的间隔提交延续索赔通知，干扰事件影响结束后36d内提交最终索赔报告",{"key":23,"text":24,"correct":14},"D","按工程师要求的间隔提交中间索赔报告，干扰事件影响结束后28d内提交最终索赔报告","2021\u002F2020教材P263页 (3)索赔事件具有连续影响的，承包人应按合理时间间隔继续递交延续索赔通知，说明连续影响的实际情况和记录，列出累计的追加付款金额和（或）工期延长天数；(4)在索赔事件影响结束后的28天内，承包人应向监理人递交最终索赔通知书，说明最终要求索赔的追加付款金额和延长的工期，并附必要的记录和证明材料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]