[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119832,789,1,"单选题","某承包商承揽的住宅工程项目，由于业主对于相关设计修改迟迟拿不定主意，致使一项工作拖期3天完工，由于该工作有3天的自由时差，根据索赔成立应该具备的前提条件，承包商()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不应向业主提出超过3天的工期索赔",false,{"key":16,"text":17,"correct":14},"B","应向业主提出费用索赔",{"key":19,"text":20,"correct":21},"C","不应向业主提出工期索赔",true,{"key":23,"text":24,"correct":14},"D","应向业主提出工期索赔","2021\u002F2020教材P262页 承包商可以提出索赔的时间有一条为：因工程变更造成的时间、费用的损失根据提议，由题意得出，未造成工期的损失。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]