[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119830,789,1,"单选题","对于设计变更引起的工程价格调整，监理公司可按照（）的原则，商定或确定变更工作的单价。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最低利润",false,{"key":16,"text":17,"correct":14},"B","市场价格",{"key":19,"text":20,"correct":21},"C","成本加利润",true,{"key":23,"text":24,"correct":14},"D","最低成本","2021\u002F2020教材P261页 七、变更的估价原则（3）已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人按第3.5款商定或确定变更工作的单价。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]