[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119827,789,1,"单选题","下列工作属于承包单位针对合同实施偏差情况，对施工合同实施趋势进行分析的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分析业主对合同偏差的态度",false,{"key":16,"text":17,"correct":14},"B","分析组织结构的变化",{"key":19,"text":20,"correct":14},"C","分析建设监理管理的严格程度",{"key":22,"text":23,"correct":24},"D","分析最终工程经济效益水平",true,"2021\u002F2020教材P261页 3.合同实施趋势分析。针对合同实施偏差情况，可以采取不同的措施，应分析在不同措施下合同执行的结构与趋势，包括：(1)最终的工程状况，包括总工期的延误、总成本的超支、质量标准、所能达到的生产能力（或功能要求）等；(2)承包商将承担什么样的后果，如被罚款、被清算，甚至被起诉，对承包商资信、企业形象、经营战略的影响等；(3)最终工程经济效益（利润）水平。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]