[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119825":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119825,789,1,"单选题","在履行合同过程中，因设计原因发生了工程变更，监理人根据合同约定情形的范围和内容，向承包人发出变更意向书。承包人则按照变更意向书要求，提交工程变更实施方案，其内容应包括拟实施变更工作的（）等内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人的指令",false,{"key":16,"text":17,"correct":14},"B","材料、设备等技术条件",{"key":19,"text":20,"correct":14},"C","设计部门的意见",{"key":22,"text":23,"correct":24},"D","计划、措施和竣工时间",true,"2021\u002F2020教材P260页 认真读懂这两页纸，理解变更程序。变更意向书应要求承包人提交包括拟实施变更工作的计划、措施和竣工时间等内容的实施方案。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]