[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119824,789,1,"单选题","根据《标准施工招标文件》的规定，监理人在收到承包人工程变更的书面建议后，确认存在变更的，应在收到书面建议后的()天内做出变更指示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","2021\u002F2020教材P260页 监理人在收到承包人工程变更的书面建议后，应与发包人共同研究，确认存在变更的，应在收到书面建议后的14天内做出变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]