[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119823,789,1,"单选题","某项目承包人，在收到变更指示的8天后，向监理人提出变更报价书。而总监理工程师在收到承包人变更报价书的第20天，约请承包人商量确定了变更价格，则在此事件中()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提交“变更报价书”超过时效",false,{"key":16,"text":17,"correct":18},"B","总监理工程师约请承包人商定变更价格超过时效",true,{"key":20,"text":21,"correct":14},"C","承包人提交“变更报价书”没有时间要求",{"key":23,"text":24,"correct":14},"D","总监理工程师约请承包人商定变更价格没有时间要求","2021\u002F2020教材P260页 监理人收到承包人书面建议后，应与发包人共同研究，确认存在变更的，应在收到承包人书面建议后的14天内作出变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]