[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119819":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119819,789,1,"单选题","“调整工作计划”属于合同实施偏差处理措施中的( )措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术",false,{"key":16,"text":17,"correct":18},"B","组织",true,{"key":20,"text":21,"correct":14},"C","经济",{"key":23,"text":24,"correct":14},"D","合同","2021\u002F2020教材P259页 根据合同实施偏差分析的结果，承包商应该采取相应的调整措施，调整措施可以分为：（1）组织措施：如增加人员投入，调整人员安排，调整工作流程和工作计划等；（2）技术措施：如变更技术方案，采用新的高效率的施工方案等；（3）经济措施：如增加投入，采取经济激励措施等；（4）合同措施：如进行合同变更，签订附加协议，采取索赔手段等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]