[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119818,789,1,"单选题","下列合同实施偏差的调整措施中，属于组织措施的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","增加资金投入",false,{"key":16,"text":17,"correct":14},"B","变更技术方案",{"key":19,"text":20,"correct":21},"C","增加人员投入",true,{"key":23,"text":24,"correct":14},"D","变更合同条款","2021\u002F2020教材P259页 根据合同实施偏差分析的结果，承包商应该采取相应的调整措施，调整措施可以分为：(1)组织措施，如增加人员投入，调整人员安排，调整工作流程和工作计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]