[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119817":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119817,789,1,"单选题","某施工合同实施过程中出现了偏差，经过偏差分析后，承包人采用新的高效率的施工方案。这种调整措施属于()措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织",false,{"key":16,"text":17,"correct":18},"B","技术",true,{"key":20,"text":21,"correct":14},"C","经济",{"key":23,"text":24,"correct":14},"D","合同","2021\u002F2020教材P259页 根据合同实施偏差分析的结果，承包商应该采取相应的调整措施，调整措施可以分为： (1)组织措施，如增加人员投入、调整人员安排、凋整工作流程和工作计划等； (2)技术措施，如变更技术方案、采用新的高效率的施工方案等； (3)经济措施，如增加投入、采取经济激励措施等； (4)合同措施，如进行合同变更、签订附加协议、采取索赔手段等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]