[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119816":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119816,789,1,"单选题","某项目实施过程中，承包人收到监理人的变更意向书，承包人认为实施该变更有困难，就立即书面通知监理人，说明变更可能对于工程价款和工期带来较大影响，并提交了相关说明和详细依据。后经监理人与承包商协商，确定撤销了原变更意向书，对此，下列表述中正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人不应对变更提出困难和异议",false,{"key":16,"text":17,"correct":14},"B","经承包人和监理人协商后可以撤销原变更意向书",{"key":19,"text":20,"correct":21},"C","撤销、改变或不改变原变更意向书都应有发包人参与协商",true,{"key":23,"text":24,"correct":14},"D","承包人对于变更提出的异议不能附加价款或工期要求","2021\u002F2020教材P260页 “若承包人收到监理人的变更意向书后认为难以实施此项变更，应立即通知监理人，说明原因并附详细依据。监理人与承包人和发包人协商后确定撤销、改变或不改变原变更意向书”和“承包人应在收到变更指示或变更意向书后14天内，向监理人提交变更报价书，报价内容应根据合同约定的估价原则，详细开列变更工作的价格组成及其依据，并附必要的施工方法说明和有关图纸” 。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]