[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119815,789,1,"单选题","在合同履行过程中，如若发生有关工程变更情形，按合同约定的变更程序，正确的做法是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人发出变更意向书，监理人提出书面变更建议",false,{"key":16,"text":17,"correct":14},"B","书面变更建议应该在收到变更意向书28天内提出",{"key":19,"text":20,"correct":21},"C","变更与否，监理人要与发包人共同研究确认",true,{"key":23,"text":24,"correct":14},"D","变更指示应在收到变更书面建议的28天做出","2021\u002F2020教材P260页 “监理人收到承包人书面建议后，应与发包人共同研究，确认存在变更的，应在收到承包人书面建议后的14天内做出变更指示”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]