[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119813":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119813,789,1,"单选题","施工合同履行过程中发生工程变更时，应由()向承包人发出变更指令。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目业主",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","监理方",true,{"key":23,"text":24,"correct":14},"D","变更提出方","2021\u002F2020教材P260页 （2）在合同履行过程中，已经发生通用合同条款第15.1款约定情形的，监理人应按照合同约定的程序向承包人发出变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]