[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119810,789,1,"单选题","关于工程变更原因的说法，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计单位新的变更指令，对建筑的新要求",true,{"key":16,"text":17,"correct":18},"B","工程环境的变化，要求实施方案或实施计划变更",false,{"key":20,"text":21,"correct":18},"C","政府部门对工程新的要求",{"key":23,"text":24,"correct":18},"D","由于合同实施出现问题，必须调整合同目标或修改合同条款","2021\u002F2020教材P259页 程变更的原因包括： (1)业主新的变更指令，对建筑的新要求； (2)由于设计人员、监理方人员、承包商事先没有很好地理解业主的意图，或设计的错误，导致图纸修改； (3)工程环境的变化，预定的工程条件不准确，要求实施方案或实施计划变更； (4)由于产生新技术和知识，有必要改变原设计、原实施方案或实施计划，或由于业主指令及业主责任的原因造成承包商施工方案的改变； (5)政府部门对工程新的要求； (6)由于合同实施出现问题，必须调整合同目标或修改合同条款。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]