[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119809":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119809,789,1,"单选题","根据《标准施工招标文件》，承包人在进行工程变更时，必须由（）做出变更指示。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","设计人",{"key":19,"text":20,"correct":21},"C","监理人",true,{"key":23,"text":24,"correct":14},"D","政府建设主管部门","2021\u002F2020教材P259页 在履行合同过程中，经发包人同意，监理人可按合同约定的变更程序向承包人作出变更指示，承包人应遵照执行。没有监理人的变更指示，承包人不得擅自变",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]