[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119808":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119808,789,1,"单选题","下列合同实施偏差的调整措施中，属于经济措施的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加人员投入",false,{"key":16,"text":17,"correct":18},"B","增加投入",true,{"key":20,"text":21,"correct":14},"C","变更技术方案",{"key":23,"text":24,"correct":14},"D","变更合同条款","2021\u002F2020教材P259页 施工合同实施偏差处理的经济措施。经济措施，如增加投入，采取经济激励措施等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]