[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119807,789,1,"单选题","施工合同实施偏差处理中，根据合同实施偏差分析的结果，承包商应该采取相应的调整措施，其中变更技术方案、采用新的高效率的施工方案属于（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","合同措施",{"key":19,"text":20,"correct":21},"C","技术措施",true,{"key":23,"text":24,"correct":14},"D","经济措施","2021\u002F2020教材P259页 三、合同实施偏差处理（2）技术措施，如变更技术方案，采用新的高效率的施工方案等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]