[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119802":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119802,789,1,"单选题","合同变更，即双方当事人依法对合同的内容进行修改的时段应是在()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程开工以后合同履行完毕以前",false,{"key":16,"text":17,"correct":14},"B","合同成立以后和工程竣工以前",{"key":19,"text":20,"correct":21},"C","合同成立以后和履行完毕以前",true,{"key":23,"text":24,"correct":14},"D","合同成立以前和履行完毕以后","2021\u002F2020教材P259页 “合同变更是指合同成立以后和履行完毕以前由双方当事人依法对合同的内容所进行的修改”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]