[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119801":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119801,789,1,"单选题","按照合同约定的变更程序，监理公司向建筑公司作出变更指示，须经( )同意。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业经理",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","设计单位",{"key":23,"text":24,"correct":14},"D","工程师","2021\u002F2020教材P259页 “根据九部委《标准施工招标文件》中通用合同条款的规定，在履行合同过程中，经发包人同意，监理人可按合同约定的变更程序向承包人作出变更指示，承包人应遵照执行。没有监理人的变更指示，承包人不得擅自变更”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]