[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119794":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119794,789,1,"单选题","承包合同计价形式的不同，工程招标时对设计深度要求也不一样，成本加酬金合同( )进行招标。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","必须在完成方案设计后",false,{"key":16,"text":17,"correct":14},"B","必须在完成初步设计后",{"key":19,"text":20,"correct":14},"C","必须在完成施工图设计后",{"key":22,"text":23,"correct":24},"D","可以在设计各个阶段",true,"2021\u002F2020教材P257页 表2Z106033中的成本加酬金合同：设计深度要求是：各设计阶段。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]