[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119793,789,1,"单选题","成本加奖金合同中的奖金是根据报价书中的成本估算指标制定的，在合同中对这个估算指标规定一个底点和顶点，分别为工程成本估算的( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","65%-75%、100%-135%",false,{"key":16,"text":17,"correct":14},"B","70%-85%、110%-155%",{"key":19,"text":20,"correct":21},"C","60%-75%、110%~135%",true,{"key":23,"text":24,"correct":14},"D","50%-65%、110%-125%","2021\u002F2020教材P256页 成本加奖金合同，估算指标规定一个底点和顶点，分别为工程成本估算的60~75%和110~135%",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]