[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119791":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119791,789,1,"单选题","通常用于紧急工程施工的是()计价方式的施工合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定单价",false,{"key":16,"text":17,"correct":18},"B","成本加酬金",true,{"key":20,"text":21,"correct":14},"C","可调价格",{"key":23,"text":24,"correct":14},"D","固定总价","2021\u002F2020教材P255页 二。成本加酬金合同特点和适用条件（2）时间特别紧迫，如抢险、救灾工程，来不及进行详细的计划和商谈。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]