[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119790":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119790,789,1,"单选题","以成本加酬金形式发包的建设工项目，其施工图纸可能不能事先完成。承包商可以通过（）缩短工期，不必等到所有施工图完成才开始招标和施工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分段施工",true,{"key":16,"text":17,"correct":18},"B","加快进度",false,{"key":20,"text":21,"correct":18},"C","增加人工",{"key":23,"text":24,"correct":18},"D","增加设备","2021\u002F2020教材P255页 二、成本加酬金合同的特点和适用条件对业主而言，这种合同形式也有一定优点。如：（1）可以通过分段施工缩短工期，而不必等待所有施工图完成才开始招标和施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]