[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119788":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119788,789,1,"单选题","某工程由于图纸、规范等准备不充分，招标方仅能制订一个估算指标，则在招标时宜采用成本加酬金合同形式中的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加奖金合同",true,{"key":16,"text":17,"correct":18},"B","成本加固定费用合同",false,{"key":20,"text":21,"correct":18},"C","成本加固定比例费用合同",{"key":23,"text":24,"correct":18},"D","最大成本加费用合同","2021\u002F2020教材P256页 3.成本加奖金合同在招标时，当图纸、规范等准备不充分，不能据以确定合同价格，而仅能制定一个估算指标时可采用成本加奖金合同这种形式。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]