[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119787":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119787,789,1,"单选题","一般在工程初期很难描述工作范围和性质，或工期紧迫，无法按常规编制招标文件招标时采用的成本加酬金合同形式是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加奖金合同",false,{"key":16,"text":17,"correct":18},"B","成本加固定比例费用合同",true,{"key":20,"text":21,"correct":14},"C","最大成本加费用合同",{"key":23,"text":24,"correct":14},"D","成本加固定费用合同","2021\u002F2020教材P256页 2.成本加固定比例费用合同工程成本中直接费加一定比例的报酬费，报酬部分的比例在签订合同时由双方确定。这种方式的报酬费用总额随成本加大而增加，不利于缩短工期和降低成本。一般在工程初期很难描述工作范围和性质，或工期紧迫，无法按常规编制招标文件招标时采用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]