[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119786,789,1,"单选题","关于成本加酬金合同的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在工程总成本一开始估计不准，可能变化不大的情况下宜采用成本加奖金合同",false,{"key":16,"text":17,"correct":18},"B","报酬总额随工程成本的加大而增加采用成本加固定比例费用合同",true,{"key":20,"text":21,"correct":14},"C","成本加固定费用合同，由于酬金金额固定，承包商在缩短工期方面没有积极性",{"key":23,"text":24,"correct":14},"D","通常在非代理型CM模式的合同中采用成本加固定费用合同","2021\u002F2020教材P256页 2.成本加固定比例费用合同：工程成本中直接费加一定比例的报酬费，报酬部分的比例在签订合同时由双方确定。这种方式的报酬费用总额随成本加大而增加，不利于缩短工期和降低成本。A是成本加固定费用合同；C，成本加固定费用合同虽然不能鼓励承包商降低成本，单位了尽快得到酬金，承包商会尽力缩短工期；D采用最大成本加费用合同。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]