[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119780,789,1,"单选题","对于应急的工程的建设，其工程承包合同的计价形式较适合采用()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总价合同",false,{"key":16,"text":17,"correct":14},"B","固定单价合同",{"key":19,"text":20,"correct":14},"C","变动单价合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"2021\u002F2020教材P255页 成本加酬金合同通常用于如下情况：（2）时间特别紧迫，如抢险、救灾工程，来不及进行详细的计划和商谈。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]