[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119777,789,1,"单选题","关于成本加酬金合同的说明,正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采用该计价方式对业主的投资控制不利",true,{"key":16,"text":17,"correct":18},"B","成本加酬金合同不适用于抢险、救灾工程",false,{"key":20,"text":21,"correct":18},"C","成本加酬金合同不宜用于项目管理合同",{"key":23,"text":24,"correct":18},"D","对承包商来说,成本加酬金合同比固定总价合同的风险高","2021\u002F2020教材P255页 成本加酬金合同,承包商不承担任何价格变化或工程量变化的风险,这些风险主要由业主承担,对业主的投资控制很不利。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]