[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119771,789,1,"单选题","某工程以固定总价合同形式发包给承包商，在工程款支付中，承包商发现因自身失误导致某项工作投标报价大大低于其合理价格。对此，承包商()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有权以合理价格为依据要求业主补差",false,{"key":16,"text":17,"correct":14},"B","有权要求对此项工作进行重新定价",{"key":19,"text":20,"correct":21},"C","无权获得任何补偿",true,{"key":23,"text":24,"correct":14},"D","可以与业主协商降低此项工作的质量标准","2021\u002F2020教材P253页 采用固定总价合同，如果由于承包商的失误导致投标价计算错误，合同总价格也不予调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]