[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119770,789,1,"单选题","如果采用单价合同，业主的工作量将会增加，主要表现在（）工作量加大。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","风险管理",false,{"key":16,"text":17,"correct":14},"B","合同管理",{"key":19,"text":20,"correct":14},"C","施工管理",{"key":22,"text":23,"correct":24},"D","核实已完成工程量",true,"2021\u002F2020教材P253页 采用单价合同对业主的不足之处是，业主需要安排专门力量来核实已经完成的工程量，需要在施工过程中花费不少精力，协调工作量大。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]