[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119769,789,1,"单选题","关于单价合同，下列选项中不正确的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单价合同实际工程款的支付以实际完成工程量乘以实际单价进行计算",true,{"key":16,"text":17,"correct":18},"B","单价合同对业主而言投资控制不利",false,{"key":20,"text":21,"correct":18},"C","单价合同的特点是单价优先",{"key":23,"text":24,"correct":18},"D","固定单价合同适用于工期短，工程量变化幅度不会太大的项目","2021\u002F2020教材P253页 采用单价合同：即单价优先。实际工程款的支付也将以实际完成工程量乘以合同单价进行计算。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]