[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119768,789,1,"单选题","某建设工程项目以单价合同形式发包，在签订合同时根据估算的工程量和单价确定了一个合同总价。工程完成后，实际完成的工程量乘以各项单价之和小于合同总价。根据单价合同的规定，工程款的支付应以()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","签订合同时确定的合同总价",false,{"key":16,"text":17,"correct":18},"B","实际完成工程量乘以各项单价之和",true,{"key":20,"text":21,"correct":14},"C","双方重新协商合同总价",{"key":23,"text":24,"correct":14},"D","实际完成工程量乘以重新协商的单价之和","2021\u002F2020教材P253页 “在工程实践中，采用单价合同有时也会根据估算的工程量计算一个初步的合同总价，作为投标报价和签订合同之用。当合同总价与各项单价乘以实际完成的工程量之和发生矛盾时，则以后者为准，即单价优先。实际工程款的支付也将以实际完成工程量乘以合同单价进行计算。”",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]