[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119767,789,1,"单选题","某建设工程项目以固定单价合同形式发包，在施工过程中主要建筑材料的价格上涨了，承包商提出了调整合同单价的要求。根据此类合同的规定业主将()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不调整合同单价",true,{"key":16,"text":17,"correct":18},"B","可以调整合同单价",false,{"key":20,"text":21,"correct":18},"C","调整涉及材料上涨的单价",{"key":23,"text":24,"correct":18},"D","调整涉及材料涨幅较大的单价","2021\u002F2020教材P253页 “固定单价合同条件下，无论发生哪些影响价格的因素都不对单价进行调整”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]