[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119766,789,1,"单选题","“单价优先”原则指：在工程实践中，采用单价合同时，当单价乘以工程量表中估算的工程量得出的初步合同总价与单价乘以实际完成的工程量之和发生矛盾时，应以( )为准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单价乘以工程量表中估算的工程量得出的初步合同总价",false,{"key":16,"text":17,"correct":18},"B","单价乘以实际完成的工程量之和",true,{"key":20,"text":21,"correct":14},"C","二者均可",{"key":23,"text":24,"correct":14},"D","视具体情况而定","2021\u002F2020教材P252页 当总价和单价的计算结果不一致时，以单价为准调整总价，意思就是当单价乘以工程量表中估算的工程量得出的初步合同总价与单价乘以实际完成的工程量之和发生矛盾时，应以单价为准。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]