[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119764":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119764,789,1,"单选题","对于采用单价合同的招标工程，如投标书中有明显的数字计算错误，业主有权先做修改再评标。当总价和单价的计算结果不一致时，正确做法是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分别调整单价和总价",false,{"key":16,"text":17,"correct":14},"B","按市场价调整单价",{"key":19,"text":20,"correct":14},"C","以总价为准调整单价",{"key":22,"text":23,"correct":24},"D","以单价为准调整总价",true,"2021\u002F2020教材P252页 虽然在投标报价、评标以及签订合同中，人们常常注重总价格，但在工程款结算中单价优先，对于投标书中明显的数字计算错误，业主有权力先作修改再评标，当总价和单价的计算结果不一致时，以单价为准调整总价。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]