[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119761,789,1,"单选题","采用单价合同指标时，对于投标书中明显的数字计算错误，业主有权力先作修改再评标，当总价和单价的计算结果不一致时，以单价为准调整总价，则这体现了单价合同( )的特点。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程量优先",false,{"key":16,"text":17,"correct":14},"B","总价优先",{"key":19,"text":20,"correct":21},"C","单价优先",true,{"key":23,"text":24,"correct":14},"D","风险均摊","2021\u002F2020教材P252页 但在工程款结算中单价优先，对于投标书中明显的数字计算错误，业主有权力先作修改再评标，当总价和单价的计算结果不一致时，以单价为准调整总价。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]