[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119754,789,1,"单选题","承包商的风险主要有两个方面，下列属于“工作量风险”的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","报价计算错误",false,{"key":16,"text":17,"correct":14},"B","漏报项目",{"key":19,"text":20,"correct":14},"C","物价和人工费上涨",{"key":22,"text":23,"correct":24},"D","工程变更",true,"2021\u002F2020教材P254页 采用固定总价合同，双方结算比较简单，但是由于承包商承担了较大的风险，因此报价中不可避免地要增加一笔较高的不可预见风险费。承包商的风险主要有两个方面：是价格风险，二是工作量风险。价格风险有报价计算错误、漏报项目、物价和人工费上涨等；工作量风险有工程量计算错误、工程范围不确定、工程变更或者由于设计深度不够所造成的误差。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]