[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119753":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119753,789,1,"单选题","对于变动总价合同的计价方式，在合同执行过程中，可以按照（）原则对合同总价进行相应的调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同约定",true,{"key":16,"text":17,"correct":18},"B","承包商实际增加的费用",false,{"key":20,"text":21,"correct":18},"C","市场行情",{"key":23,"text":24,"correct":18},"D","监理工程师出具的承包商费用增加证明","2021\u002F2020教材P254页 “在合同执行过程中，由于通货膨胀等原因而使工、料成本增加时，可以按照合同约定对合同总价进行相应的调整”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]