[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119752,789,1,"单选题","某工程以固定总价合同形式发包给承包商，在夏季施工中，雨天较往年多，许多费用较投标时预计的高。为此，承包商()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有权要求将增加的费用加到合同总价中",false,{"key":16,"text":17,"correct":18},"B","无权要求将增加的费用加到合同总价中",true,{"key":20,"text":21,"correct":14},"C","增加的费用需通过业主的审核后才能加到合同总价中",{"key":23,"text":24,"correct":14},"D","可以与业主协商解决费用增加的补偿问题","2021\u002F2020教材P254页 “采用固定总价合同，双方结算比较简单，但是由于承包商承担了较大的风险，因此报价中不可避免地要增加一笔较高的不可预见风险费”和“承包商在报价时对一切费用的价格变动因素以及不可预见因素都做了充分估计，并将其包含在合同价格之中”，由题意知雨水较往年多属于不可预见因素，所以承包商无权要求增加费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]