[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119750":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119750,789,1,"单选题","某建设工程项目采用固定单价合同。工程完工后，实际完成的工程量乘以各项单价之和与合同总价不一致。在此情况下，工程款的结算应以()为准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同总价",false,{"key":16,"text":17,"correct":18},"B","实际完成工程量乘以各项单价之和",true,{"key":20,"text":21,"correct":14},"C","双方重新协商合同总价",{"key":23,"text":24,"correct":14},"D","实际完成工程量乘以重新协商的单价之和","2021\u002F2020教材P253页 在工程实践中，采用单价合同有时也会根据估算的工程量计算一个初步的合同总价，作为投标报价和签订合同之用。但是，当上述初步的合同总价与各项单价乘以实际完成的工程量之和发生矛盾时，则肯定以后者为准.即单价优先。实际工程款的支付也将以实际完成工程量乘以合同单价进行计算。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]