[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119747":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119747,789,1,"单选题","对于固定总价合同的计价方式，承包商为了降低自己在工程量和价格上承担的风险，通常会在合同报价中报较高的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施费",false,{"key":16,"text":17,"correct":18},"B","不可预计风险费",true,{"key":20,"text":21,"correct":14},"C","单价",{"key":23,"text":24,"correct":14},"D","管理费","2021\u002F2020教材P253页 合同总价一次包死，固定不变，即不再因为环境的变化和工程量的增减而变化。在这类合同中承包商承担了全部的工作量和价格的风险，因此，承包商在报价时对一切费用的价格变动因素以及不可预见因素都做了充分估计，并将其包含在合同价格之中。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]